Chapter 3 'So You Want to Build a Shop!'
by Maurice Clyma

It has taken quite a while to gather up the cost information
from all the separate sources. Since I
will be building part of the shop, I had to get separate prices on all the
materials as well as the costs for the contracted work. As I said previously, this
is the reality
check.
I received one price from a
contractor to provide the excavation, footings and concrete slab with a separate
price for providing labor only for all the framing, sheathing siding, window
& door installation, and siding that
was more than my total budget and I still had to buy all the material. Obviously I
get to build more of the project
than originally intended.
The cost of
materials were obtained from Home Depot and M&M Lumber Co. These included free
engineering for the roof
and floor framing. As near as I can tell
the estimates were within $250 of each other. I have also decided to eliminate
the storage loft and the extra wall
height to reduce the cost of materials. This will bring the wall height down
to 8’ and make it easier for me to
do the framing. I have not had to reduce
the size of the shop and I have been able to retain the dust collection and
compressed air systems.
I have included
floor plans and elevations of the revised design.
Editor's note...click on the following links to see Maurice's floor plans and
elevations for his shop. You will need
Adobe Acrobat Reader
to view these files. You can download Reader by clicking
here.
Floor Plans
Shop Elevation 1
Shop Elevation 2
These changes of course
require an amendment to the building permit. There were several things that ate
into the shop budget; Tree removal,
demolition of the patio slab destroyed by said tree roots, replacement of the
patio slab and the sewer replacement.
While waiting on the costs to arrive I got the sanitary sewer
from the house replaced where it will run under the shop building and I have
assembled the dust collection ducts that will run under the floor slab. This was relatively easy except for
determining the exact length to cut the PVC pipe to locate the risers where they
will be close to the planned equipment locations. I had no information that gave me dimensions
of the all the joints and elbows so these had to be measured after
purchase. I also assembled the under
floor conduit for the one electrical outlet location away from a wall.
I am now ready for the contractor who is
going to start Thursday on the foundations and floor slab.
The contractor said that he will set the dust
collection system and the conduit in place. That way he will not have to wait on me.
He plans to have the slab poured by Saturday. I have contacted a termite treatment company
to treat the soil before the concrete is poured. I now have to recalculate the framing
material and place an order for delivery next week. I also need to have rough-in dimensions for
the doors and wall air conditioning unit. The windows will be built on site to fit the openings.
Home Depot has cordless compressed air
framing nailers for rent at $25/day as well as any other tools I might
need.
I am looking forward to finally getting started and will keep
you advised on progress and problems.
Chapter 4
|